NO
|
URAIAN PEKERJAAN
|
SAT
|
KOEF
|
VOL
|
JUMLAH
VOLUME
|
A090
|
1 m2 Pekerjaan
Pengecetan dinding 2x
|
||||
Cat Tembok
Plamir Tembok
Roll Cat
Steiger Werk
Ampelas
Pekerja
Pekerja Trampil
Tukang
Mandor
|
Kg
Kg
Bh
Ls
Lbr
HOK
HOK
HOK
HOK
|
0.1225
0.1120
0.0070
0.0450
0.3500
0.0728
0.1274
0.0137
0.0070
|
720 m2
|
88.0
80.64
5.04
32.4
252
52.416
91.728
9.864
5.04
|
|
A091
|
1 m2 Pekerjaan
Pengecetan Plafoun 2x
|
||||
Cat Kayu
Dempul Kayu
Roll Cat
Steiger Werk
Ampelas
Pekerja
Pekerja Terampil
Tukang
Mandor
|
Kg
Kg
Bh
Ls
Lbr
HOK
HOK
HOK
HOK
|
0.1400
0.1120
0.0070
0.0450
0.3500
0.0728
0.1274
0.0137
0.0070
|
364 m2
|
50.96
40.768
2.548
16.38
127.4
26.4992
46.3736
4.9868
2.548
|
|
A066
|
1 m3 Pas Kayu
bag. Atas (Kuda-kuda), Kayu sekualitas borneo super
|
||||
Kayu borneo super
Paku
Pekerja
Pekerja Terampil
Tukang
Mandor
|
m3
Kg
HOK
HOK
HOK
HOK
|
1.1000
5.8000
3.0000
5.0000
2.0000
0.4000
|
2.19024 m3
|
2.409264
12.70339
6.57072
10.9512
4.38048
0.876096
|
|
A069
|
1 m3 Pas Lispang
Kayu Ukuran 3/20 cm Kayu kamper banjar
|
||||
Papan kayu kamper banjar
Paku
Pekerja Terampil
Tukang
Mandor
|
m3
Kg
HOK
HOK
HOK
|
0.0070
0.0100
0.0700
0.0200
0.0040
|
80 m
|
0.56
0.8
5.6
1.6
0.32
|
A072
|
1 m2 Pas Asbes
gelombang 1.80 mm x 0.90 mm
|
||||
Asbes
Paku
Pekerja
Tukang
Mandor
|
Bh
Kg
HOK
HOK
HOK
|
0.7500
0.0150
0.1500
0.0750
0.0080
|
364 m2
|
273
5.46
54.6
27.3
2.912
|
|
A076
|
1 m2 Pas Bubung
genteng morando natural
|
||||
Bubung Gneteng Morando
PC
Pasir Pasang
Pekerja Terampil
Tukang
Mandor
|
Bh
Zak
m3
HOK
HOK
HOK
|
4.0000
0.1304
0.2100
0.1500
0.2000
0.0050
|
26 m
|
104
3.3904
5.46
3.9
5.2
0.13
|
|
A082
|
1 m2 Pas Plafoun
Triplek 3 mm berikut rangka kayu kelas II
|
||||
Triplek 3 mm
Kayu Kaso 5/7 borneo super
Kayu Kaso 5/10
Paku
Pekerja Terampil
Tukang
Mandor
|
Lbr
m3
m3
Kg
HOK
HOK
HOK
|
0.3472
0.0140
0.0035
0.2200
0.2800
0.4000
0.0140
|
364 m2
|
126.3808
5.096
1.274
80.08
101.92
145.6
5.096
|
NO
|
URAIAN BAHAN/PEKERJAAN
|
HARGA
SATUAN
|
JUMLAH
VOLUME
|
JUMLAH
HARGA
|
1
|
Cat Tembok
|
75.000/Kg
|
88.2
Kg
|
6.615.000
|
2
|
Plamir Tembok
|
30.000/Kg
|
80.64
Kg
|
2.419.200
|
3
|
Cat Kayu
|
55.000/Kg
|
50.96
Kg
|
2.802.800
|
4
|
Dempul Kayu
|
13.500/Kg
|
40.768
Kg
|
550.300
|
5
|
Roll Cat
|
12.500/Bh
|
8 Bh
|
100.000
|
6
|
Steiger Werk
|
17.000/Ls
|
48
Ls
|
816.000
|
7
|
Ampelas
|
5.000/Lbr
|
379
Lbr
|
1.895.000
|
8
|
Kayu borneo super
|
4.750.000/m3
|
2.4
m3
|
11.400.000
|
9
|
Paku
|
12.500/Kg
|
99
Kg
|
1.237.500
|
10
|
Papan kamper banjar
|
5.900.000/m3
|
0.56
m3
|
3.304.000
|
11
|
Kaso 5/7 borneo super
|
4.000.000/m3
|
6.37
m3
|
25.480.000
|
12
|
Asbes 1.8 mm x 0.80 mm
|
50.000/Lbr
|
273
Lbr
|
13.650.000
|
13
|
Bubungan morando
|
4.000/Bh
|
104
Bh
|
416.000
|
14
|
Semen 50 Kg
|
55.000/Zak
|
4
Zak
|
220.000
|
15
|
Pasir Pasang
|
150.000/m3
|
5.46
m3
|
819.000
|
16
|
Triplek 3 mm x 12 x 240
|
55.000/Lbr
|
127
Lbr
|
6.985.000
|
17
|
Pekerja
|
35.000/HOK
|
140
HOK
|
4.900.000
|
18
|
Pekerja Terampil
|
40.000/HOK
|
260
HOK
|
10.400.000
|
19
|
Tukang
|
45.000/HOK
|
199
HOK
|
8.955.000
|
20
|
Mandor
|
50.000/HOK
|
17
HOK
|
850.000
|
21
|
Administrasi Proposal
|
500.000/Ls
|
1 Ls
|
500.000
|
22
|
Perencanaan + RAB
|
250.000/Ls
|
1 Ls
|
250.000
|
Jumlah
|
104.564.800
|
|||
Dibulatkan
|
104.564.800
|